1、Chapter 6Investment Decision Rules6-2 Chapter Outline6.1 NPV and Stand-Alone Projects6.2 The Internal Rate of Return Rule6.3 The Payback Rule6.4 Choosing Between Projects6.5 Project Selection with Resource Constraints6-3 Learning Objectives1.Define net present value,payback period,internal rate of r
2、eturn,profitability index,and incremental IRR.2.Describe decision rules for each of the tools in objective 1,for both stand-alone and mutually exclusive projects.3.Given cash flows,compute the NPV,payback period,internal rate of return,and profitability index for a given project,and the incremental
3、IRR for a pair of projects.6-4 Learning Objectives4.Compare each of the capital budgeting tools above,and tell why NPV always gives the correct decision.5.Discuss the reasons IRR can give a flawed decision.6.Describe situations in which profitability index cannot be used to make a decision.6-5 6.1 N
4、PV and Stand-Alone Projects Consider a take-it-or-leave-it investment decision involving a single,stand-alone project for Fredricks Feed and Farm(FFF).The project costs$250 million and is expected to generate cash flows of$35 million per year,starting at the end of the first year and lasting forever
5、.6-6 NPV Rule The NPV of the project is calculated as:The NPV is dependent on the discount rate.35NPV 250 6-7 Figure 6.1 NPV of Fredricks Fertilizer ProjectIf FFFs cost of capital is 10%,the NPV is$100 million and they should undertake the investment.6-8 Alternative Rules Versus the NPV Rule Sometim
6、es alternative investment rules may give the same answer as the NPV rule,but at other times they may disagree.When the rules conflict,the NPV decision rule should be followed.6-9 6.2 The Internal Rate of Return Rule Internal Rate of Return(IRR)Investment Rule Take any investment where the IRR exceed
7、s the cost of capital.Turn down any investment whose IRR is less than the cost of capital.6-10 The Internal Rate of Return Rule(contd)The IRR Investment Rule will give the same answer as the NPV rule in many,but not all,situations.In general,the IRR rule works for a stand-alone project if all of the
8、 projects negative cash flows precede its positive cash flows.In Figure 6.1,whenever the cost of capital is below the IRR of 14%,the project has a positive NPV and you should undertake the investment.6-11 Applying The IRR Rule In other cases,the IRR rule may disagree with the NPV rule and thus be in
9、correct.Situations where the IRR rule and NPV rule may be in conflict:Delayed Investments Nonexistent IRR Multiple IRRs6-12 Applying The IRR Rule(contd)Delayed Investments Assume you have just retired as the CEO of a successful company.A major publisher has offered you a book deal.The publisher will
10、 pay you$1 million upfront if you agree to write a book about your experiences.You estimate that it will take three years to write the book.The time you spend writing will cause you to give up speaking engagements amounting to$500,000 per year.You estimate your opportunity cost to be 10%.6-13 Applyi
11、ng The IRR Rule(contd)Delayed Investments Should you accept the deal?Calculate the IRR.The IRR is greater than the cost of capital.Thus,the IRR rule indicates you should accept the deal.6-14 CFj1000000Gold-500000CFj3IRRGold23.38NjFinancial Calculator Solution6-15 Applying The IRR Rule(contd)Delayed
12、Investments Should you accept the deal?Since the NPV is negative,the NPV rule indicates you should reject the deal.23500,000500,000500,000 1,000,000$243,4261.11.11.16-16 Figure 6.2 NPV of Stars$1 Million Book DealWhen the benefits of an investment occur before the costs,the NPV is an increasing func
13、tion of the discount rate.6-17 Applying The IRR Rule(contd)Multiple IRRs Suppose Star informs the publisher that it needs to sweeten the deal before he will accept it.The publisher offers$550,000 advance and$1,000,000 in four years when the book is published.Should he accept or reject the new offer?
14、6-18 Applying The IRR Rule(contd)Multiple IRRs The cash flows would now look like:The NPV is calculated as:234500,000500,000500,0001,000,000 550,000-1 (1 )(1 )(1 )NPVrrrr6-19 Applying The IRR Rule(contd)Multiple IRRs By setting the NPV equal to zero and solving for r,we find the IRR.In this case,the
15、re are two IRRs:7.164%and 33.673%.Because there is more than one IRR,the IRR rule cannot be applied.6-20 Figure 6.3 NPV of Stars Book Deal with Royalties6-21 Applying The IRR Rule(contd)Multiple IRRs Between 7.164%and 33.673%,the book deal has a negative NPV.Since your opportunity cost of capital is
16、 10%,you should reject the deal.6-22 Applying The IRR Rule(contd)Nonexistent IRR Finally,Star is able to get the publisher to increase his advance to$750,000,in addition to the$1 million when the book is published in four years.With these cash flows,no IRR exists;there is no discount rate that makes
17、 NPV equal to zero.6-23 Figure 6.4 NPV of Stars Final OfferNo IRR exists because the NPV is positive for all values of the discount rate.Thus the IRR rule cannot be used.6-24 Applying The IRR Rule(contd)IRR Versus the IRR Rule While the IRR rule has shortcomings for making investment decisions,the I
18、RR itself remains useful.IRR measures the average return of the investment and the sensitivity of the NPV to any estimation error in the cost of capital.6-25 Textbook Example 6.16-26 Textbook Example 6.1(contd)6-27 6.3 The Payback Rule The payback period is amount of time it takes to recover or pay
19、back the initial investment.If the payback period is less than a pre-specified length of time,you accept the project.Otherwise,you reject the project.The payback rule is used by many companies because of its simplicity.6-28 Textbook Example 6.26-29 Textbook Example 6.2(contd)6-30 Alternative Example
20、 6.2 Problem Projects A,B,and C each have an expected life of 5 years.Given the initial cost and annual cash flow information below,what is the payback period for each project?ABCCost$80$120$150Cash Flow$25$30$356-31 Alternative Example 6.2 Solution Payback A$80$25=3.2 years Project B$120$30=4.0 yea
21、rs Project C$150$35=4.29 years6-32 The Payback Rule(contd)Pitfalls:Ignores the projects cost of capital and time value of money.Ignores cash flows after the payback period.Relies on an ad hoc decision criterion.6-33 6.4 Choosing Between Projects Mutually Exclusive Projects When you must choose only
22、one project among several possible projects,the choice is mutually exclusive.NPV Rule Select the project with the highest NPV.IRR Rule Selecting the project with the highest IRR may lead to mistakes.6-34 Textbook Example 6.36-35 Textbook Example 6.3(contd)6-36 IRR Rule and Mutually Exclusive Investm
23、ents:Differences in Scale If a projects size is doubled,its NPV will double.This is not the case with IRR.Thus,the IRR rule cannot be used to compare projects of different scales.6-37 IRR Rule and Mutually Exclusive Investments:Differences in Scale(contd)Consider two of the projects from Example 6.3
24、BookstoreCoffee ShopInitial Investment$300,000$400,000Cash FlowYear 1$63,000$80,000Annual Growth Rate3%3%Cost of Capital8%8%IRR24%23%NPV$960,000$1,200,0006-38 IRR Rule and Mutually Exclusive Investments:Timing of Cash Flows Another problem with the IRR is that it can be affected by changing the timi
25、ng of the cash flows,even when the scale is the same.IRR is a return,but the dollar value of earning a given return depends on how long the return is earned.Consider again the coffee shop and the music store investment in Example 6.3.Both have the same initial scale and the same horizon.The coffee s
26、hop has a lower IRR,but a higher NPV because of its higher growth rate.6-39 IRR Rule and Mutually Exclusive Investments:Differences in Risk An IRR that is attractive for a safe project need not be attractive for a riskier project.Consider the investment in the electronics store from Example 6.3.The
27、IRR is higher than those of the other investment opportunities,yet the NPV is the lowest.The higher cost of capital means a higher IRR is necessary to make the project attractive.6-40 The Incremental IRR Rule Incremental IRR Investment Rule Apply the IRR rule to the difference between the cash flows
28、 of the two mutually exclusive alternatives(the increment to the cash flows of one investment over the other).6-41 Textbook Example 6.46-42 Textbook Example 6.4(contd)6-43 Comparison of Minor and Major OverhaulsFigure 6.5 NPV Profiles for Example 6.16-44 Alternative Example 6.4Suppose your firm is c
29、onsidering two different projects,one that lasts one year and another that lasts five years.The cash flows for the two projects look like this:What is the IRR of each proposal?What is the incremental IRR?If your firms cost of capital is 10%,what should you do?Problem:6-45 Alternative Example 6.4Solu
30、tion:We can compute the IRR of Project L using the annuity calculator:NPERRATEPVPMTFVExcel formulaGiven5-1000200Solve for rate14.87%=RATE(5,0,-100,200)6-46 Alternative Example 6.4(contd)Solution(contd):We can compute the IRR of Project S using the annuity calculator:NPERRATEPVPMTFVExcel formulaGiven
31、1-1000125Solve for rate25%=RATE(1,0,-100,125)6-47 Alternative Example 6.4(contd)Solution(contd):We can calculate the incremental IRR this way:NPERRATEPVPMTFVExcel formulaGiven4-1250200Solve for rate12.47%=RATE(4,0,-125,200)Project 012345L-100200S-100125Difference0-1252006-48 Alternative Example 6.4(
32、contd)Solution(contd)Because the 12.47%incremental IRR is bigger than the cost of capital of 10%,the long-term project is better than the short-term project,even though the short-term project has a higher IRR.6-49 The Incremental IRR Rule(contd)Shortcomings of the Incremental IRR Rule The incrementa
33、l IRR may not exist.Multiple incremental IRRs could exist.The fact that the IRR exceeds the cost of capital for both projects does not imply that either project has a positive NPV.When individual projects have different costs of capital,it is not obvious which cost of capital the incremental IRR sho
34、uld be compared to.6-50 6.5 Project Selection with Resource Constraints Evaluation of Projects with Different Resource Constraints Consider three possible projects with a$100 million budget constraintTable 6.1 Possible Projects for a$100 Million Budget6-51 Profitability Index The profitability index
35、 can be used to identify the optimal combination of projects to undertake.From Table 6.1,we can see it is better to take projects II&III together and forego project I.Value CreatedNPVProfitability Index Resource ConsumedResource Consumed6-52 Textbook Example 6.56-53 Textbook Example 6.5(contd)6-54 A
36、lternative Example 6.5 Problem Suppose your firm has the following five positive NPV projects to choose from.However,there is not enough manufacturing space in your plant to select all of the projects.Use profitability index to choose among the projects,given that you only have 100,000 square feet o
37、f unused space.ProjectNPVSquare feet neededProject 1100,00040,000Project 288,00030,000Project 380,00038,000Project 450,00024,000Project 512,0001,000Total330,000133,0006-55 Alternative Example 6.5(contd)Solution Compute the PI for each project.ProjectNPVSquare feet neededProfitability Index(NPV/Sq.Ft
38、)Project 1100,00040,0002.5Project 288,00030,0002.93Project 380,00038,0002.10Project 450,00024,0002.08Project 512,0001,00012.0Total330,000133,0006-56 Alternative Example 6.5(contd)Solution Rank order them by PI and see how many projects you can have before you run out of space.ProjectNPVSquare feet n
39、eededProfitability Index(NPV/Sq.Ft)Cumulative total space usedProject 512,0001,0002.51,000Project 288,00030,0002.9331,000Project 1100,00040,0002.571,000Project 380,00038,0002.11Project 450,00024,0002.086-57 Shortcomings of the Profitability Index In some situations the profitability Index does not g
40、ive an accurate answer.Suppose in Example 6.4 that NetIt has an additional small project with a NPV of only$120,000 that requires 3 engineers.The profitability index in this case is 0.1 2/3=0.04,so this project would appear at the bottom of the ranking.However,3 of the 190 employees are not being us
41、ed after the first four projects are selected.As a result,it would make sense to take on this project even though it would be ranked last.6-58 Shortcomings of the Profitability Index(contd)With multiple resource constraints,the profitability index can break down completely.6-59 Discussion of Data Ca
42、se Key Topic On February 9,2006,XM Satellite announced a three-year,$55 million deal with Oprah Winfrey.The announcement stated that“Oprah&Friends,”a new channel on XM,would begin broadcasting in September 2006.What was the change in XMs market value from January 30,2006 through February 10,2006?Doe
43、s the$55 million investment appear to have been a good idea?http:/ Chapter Quiz1.Explain the NPV rule for stand-alone projects.2.If the IRR rule and the NPV rule lead to different decisions for a stand-alone project,which should you follow?Why?3.For mutually exclusive projects,explain why picking on
44、e project over another because it has a larger IRR can lead to mistakes.4.Explain why ranking projects according to their NPV might not be optimal when you evaluate projects with different resource requirements.5.How can the profitability index be used to identify attractive projects when there are resource constraints?