1、DIAR DUSHANBE PROJECT PHASE 1Ref No: SHY/DDP/PE1/12/138 Date: 22nd Nov. 2012To: Mr. Sadettin Otluoglu Resident EngineerDAR Muhendislik Musavirlik A.S.AINI Street 24a “Markazai Tijori” CJSC “S.A.S”, 3rd FloorDushanbe, Tajikistan 734012Tel: +992(44)601 92 88RE: Contract ID: 55002348 Construction of Di
2、ar Dushanbe Project - Phase1Subject: Resubmission of Contractors Construction Programme (Version 03) Your Ref.: Letter QDDP-IMS-SNH-121005-794 dated on 5th Oct. 2012 Letter TJ10079/S/691 dated on 5th Nov. 2012 Letter QDDP-IMS-SNH-121113-860 dated on 13th Nov. 2012Other Ref.: Our letter SHY/DDP/PE1/1
3、2/060 dated on 5th Sep. 2012 Our letter SHY/DDP/PE1/12/118 dated on 7th Nov. 2012_Dear Sir,Your response to our letter 118 has been duly noted by the Contractor and we hereby resubmit the Programme in accordance with the Sub-Clause 8.3 for your review and approval. Please be noted that break-down of
4、 the WBS, all activities, the resource allocation/loading & monetary value of activity (coordinated with the BOQ) and any necessary reports as requested have been reasonably incorporated. Besides that, we kindly draw your attention to the Sub-Clause 8.3 “The Contractor shall promptly give notice to
5、the Engineer of specific probable future events or circumstances which may adversely affect the work, increase the Contract Price or delay the execution of the Works.”, and you may understand that the coming winter season shall be considered as a future circumstances which will adversely affect the
6、work. Please evaluate the same in these respects and accordingly, we will submit the revised Programme in accordance with Sub-Clause .8.6 in due course. Assuring you our best cooperation at all times, as always.Yours faithfully,Project Manager of * Tajikistan Cor. LimitedEnclosures: 1. Construction Programme (A3 size, ?pages)2. Necessary Supporting Reports CC: Mr. Rakesh Pant, QD Project ManagerMr. Ahmet Ziya Akyil, IMS Project Manager