1、Heading CORPORATION LIMITEDDIAR DUSHANBE PROJECT PHASE 1Ref No: SHY/DDP/PE1/12/1* Date: December 19, 2012To: Mr. * Resident EngineerDAR Muhendislik Musavirlik A.S.AINI Street 24a “Markazai Tijori” CJSC “S.A.S”, 3rd FloorDushanbe, Tajikistan 734012Tel: +992(44)601 92 88RE: Contract ID: 55002348 Const
2、ruction of Diar Dushanbe Project - Phase1Subject: Notice of Claim No.2- Extension of Time Our Ref.: SHY/DDP/PE1/12/113dated on 5th November, 2012 SHY/DDP/PE1/12/134 dated on 17th November, 2012Your Ref.: QDDP-IMS-SNH-120816-630 dated on 16th August 2012 QDDP-IMS-SNH-120921-746 dated on 21st Septembe
3、r 2012 QDDP-IMS-SNH-121205-900 dated on 5th December 2012 _Dear Sir,Reference is made to your Ref. 900 dated on 5th December 2012 and your comments have been duly noted. Following the latest communication and mutual understanding, we hereby give you the Notice of Claim (labelled as Claim No.2) relat
4、ed to the Event as described in our Ref 113 &134 under Sub-Clause20.1, which is arising from Sub-Clause 2.1 of Conditions of Contract. We understand that the Employer should give the Contractor right of access to, and possession of, all parts of the Sites within the time stated in the Appendix to Te
5、nder-quote “Time for access to the Site 2.1 Section 1:1 Day from Commencement Date (D+1); Section 2: 1 Day from Commencement Date (D+1).” It is recalled that the Engineer has issued the NTP on 6th August 2012 regardless of the conditions precedent to Commencement under the Contract and the Contracto
6、r has not possessed the Site until 21st September 2012. Definitely the Contractor has suffered delay and incurred additional Cost as a result of a failure to get access to Site according to the Sub-Clause 2.1. The Contractor shall be entitled subject to Sub-Clause 20.1Contractors Claims to:i) 36days
7、 of Extension of time as per (b) & (e) under Sub-Clause 8.4Extension of Time for Completion, andii) Payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.” (We reserved such entitlement.)You are kindly requested to proceed in accordance with Sub-Clause 3.5 Determinations to agree or determine Claim No.2 as soon as possible. Yours faithfully,* Project Manager of * Corporation LimitedEnclosures: All the references as listed here-aboveCC: Mr. *, QD Project ManagerMr. *, IMS Project Manager E-mail: